1. Routine repair of TG-4 in 1995.
2. Diagnostic measurements of TG-3 and TG-4; 1996 and 1999.
3. Diagnostic measurements of TG-4; 1997 and 1998.
4. Diagnostic measurements of TG-2; 2000.
5. Installation of a new TG-1 block; 2006.
6. Major overhaul of TG-2; 2008.
ZP Świecie heat and power plant
Stalowa Wola heat and power plant
1. Installation of the TG-6 turbo set (40MW).
2. Major overhauls of the TG-5, TG-7 and TG-8 turbines.
ZML Kęty SA
1. Measuring and setting a hydraulic press; 2006.
2. Setting technological “tables” in 2007, 2008 and 2009.
Rzeszów SA heat and power plant
Servicing the installation of TG-1 in 2002 and its routine repair in 2005.
Bydgoszcz heat and power plant:
Servicing the major overhauls and modernization of TG-1 and TG-2; 2001 and 2002.