Blachownia power plant:

1. Major overhauls of turbo sets TG-3, TG-4, TG-7 and TG-8.

Siersza power plant:

1. Overhaul and modernization of turbo sets TG-1, TG-2, TG-3, TG-4, TG-5 and TG-6.
2. Regular diagnostic measurements of shaft alignment of turbo sets TG-1, TG-2, TG-3, TG-4, TG-5 and TG-6 and the
foundations and reference points on TG-1 and TG-2.
3. Major overhauls of all turbo sets.

Skawina power plant:

1. Overhaul and modernization of TG-1 and TG-2.
2.  Installation of turbines WK-100-6M  -TG-3, TG-4, TG-5, TG-6; 1993-1996.

Łaziska power plant:

1. Current major overhauls of turbo sets TG-1, TG-2 (120 MW) and TG-9, TG-10, TG-11, TG-12 (215 MW).
2. Overhaul and modernization of TG-9, TG-10, TG-11 and TG-12 blocks; 1995-2000, for Alstom Power (former Zamech, ABB Zamech, ABB Alstom).
3. Measurements of the spatial position of the condenser walls on TG-9 and TG-11.
4. Constant diagnostic measurements of all turbines.

Ostrołęka A and B power plants:

1. Repairs of turbines in the 1980s and 1990s (non-stop).
2. Current repairs of turbo sets TG-1, TG-2 and TG-3 (200 MW).
3. Current major overhauls of medium-power turbo sets at Ostrołęka A.
4. Modernization of turbines TG-1 and TG-3 for Westinghouse.

Będzin power plant:

1. Measurements of relative vertical dislocations of a turbogenerator (1993-end of 1998).

Żerań power plant:

1. Repairs of turbo sets TG-1 and TG-5.

Siekierki heat and power plant:

1. Servicing major overhauls of TG-1 to TG-5.

Miechowice heat and power plant:

1. Installation of turbo set TG-3 (100MW).
2. Repair of turbo set TG-3 (100MW).
3. Measuring relative dislocations of TG-2; 1995 and 1996.

Gdynia SA heat and power plant

1. Servicing the major overhaul of TG-1; 2002.
2. Servicing the generator exchange; 2007.

Gorzów Wielkopolski heat and power plant:

1. Installation of the TG-1 turbo set; 2007.

Bydgoszcz heat and power plant:

1. Servicing the major overhauls and modernization of TG-1 and TG-2; 2001 and 2002.

Zielona Góra heat and power plant:

1. Installation of turbo set TG-1 (80 MW); 2003.

Rzeszów SA heat and power plant:

1. Servicing the installation of TG-1 in 2002 and its routine repair in 2005.

Steelworks – heat and power plant, Nowa Huta:

1. Repair of a turbo set; 2003.

Janikowo – Soda heat and power plant

1. Servicing the major overhauls of TG-1 to TG-3.